A $400 million cement plant in Zambia owned by Dangote Group will be commissioned and commence operations by the end of March, according to a report by the Lusaka Times.
Speaking to a group of Journalists on Thursday at departure at Simon Mwansa Kapwepwe International Airport in Ndola, Aliko Dangote, Africa’s richest man and owner of the Dangote Group, said that the commissioning of the new cement plantwhich is located in Masaiti district in the Copperbelt, had been delayed as a result of flooding and a delay in getting the requisite permits from the Zambia Environmental Management Agency (ZEMA).
Once operational, the Dangote Cement Plant will have a production capacity of 1.5 million tonnes annually and will create at least 1,000 jobs.
Meanwhile, Dangote is constructing another Cement Plant in Chilanga, a small town 20 km south of Zambia’s capital city, Lusaka. The cement plant in Chilanga will cost an estimated $420 million.
“We have made good progress on the plant in Lusaka, we have already got permission to get into the land and start mining, so hopefully the same contractor might move there and build an identical plant with the one in Masaiti,” Dangote said.